Plan fewer, bigger changes #251

Closed
opened 2026-10-27 15:30:58 -04:00 by cmoriarty · 1 comment
Owner

What happens
The pinball plan cut the brief into six thin layers, one run each: skeleton, physics, input, table features, scoring, lighting.

  • The first run chose a "plain table" and said polished visuals "come later".
  • The only later item for the look was "lights and sound tied to hits". The placeholder look stayed.

Cost
64.6 min unattended. The same brief as one change took 22.0 min, and looked far better.

What we want

  • Fewer, bigger changes. Each one is a slice of the whole app that someone can try.
  • A small project stays one change.
  • When the brief asks for a look, the plan states an art direction.

Done when
The pinball brief plans as one to three changes, each playable, with the look there from the first.

From the Braid vs Claude Code pinball test, 2026-10-27 (runs 110–120).

**What happens** The pinball plan cut the brief into six thin layers, one run each: skeleton, physics, input, table features, scoring, lighting. - The first run chose a "plain table" and said polished visuals "come later". - The only later item for the look was "lights and sound tied to hits". The placeholder look stayed. **Cost** 64.6 min unattended. The same brief as one change took 22.0 min, and looked far better. **What we want** - Fewer, bigger changes. Each one is a slice of the whole app that someone can try. - A small project stays one change. - When the brief asks for a look, the plan states an art direction. **Done when** The pinball brief plans as one to three changes, each playable, with the look there from the first. _From the Braid vs Claude Code pinball test, 2026-10-27 (runs 110–120)._
Author
Owner

What shipped

  • A plan's Now milestone holds 1 to 3 items (it was 3 to 7).
  • The first item is a working version of the whole project, built to the quality the brief asks for, its look included.
  • Each item is a slice someone can try, not a layer, and a project one run can build is one item.
  • A brief that asks for a look gets an art direction under Assumptions.

Test
tests/pipeline/test_plan.py.

Shipped in 5598ddf (OpenSpec change iterative-planned-projects, archived).

**What shipped** - A plan's Now milestone holds 1 to 3 items (it was 3 to 7). - The first item is a working version of the whole project, built to the quality the brief asks for, its look included. - Each item is a slice someone can try, not a layer, and a project one run can build is one item. - A brief that asks for a look gets an art direction under Assumptions. **Test** `tests/pipeline/test_plan.py`. _Shipped in 5598ddf (OpenSpec change `iterative-planned-projects`, archived)._
Sign in to join this conversation.
No labels
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set

Reference
cmoriarty/braid#251
No description provided.