While a project writes its plan, its page says 'No plan is left on disk' #318

Closed
opened 2026-10-29 20:38:11 -04:00 by cmoriarty · 1 comment
Owner

What happens
While run 146 wrote the Breakout project's plan (16:35-16:41), the project page read "No plan is left on disk for this project." and "0 of 0 items". The plan was being written, not gone. Project.tsx shows that sentence whenever the project has no plan, whatever the reason.

Fix
While the plan run is still going, show the planning as a state, not a sentence: the plan step's row (running, its time), as the run page draws it. Keep "No plan is left on disk" for a finished project whose files were reclaimed.

Done when
A project whose plan step is running shows that step running, and no "left on disk" or "0 of 0"; a browser spec covers it.

**What happens** While run 146 wrote the Breakout project's plan (16:35-16:41), the project page read "No plan is left on disk for this project." and "0 of 0 items". The plan was being written, not gone. `Project.tsx` shows that sentence whenever the project has no plan, whatever the reason. **Fix** While the plan run is still going, show the planning as a state, not a sentence: the plan step's row (running, its time), as the run page draws it. Keep "No plan is left on disk" for a finished project whose files were reclaimed. **Done when** A project whose plan step is running shows that step running, and no "left on disk" or "0 of 0"; a browser spec covers it.
Author
Owner

Confirmed on production (1fc0f22, PR #319); closing. While run 148 wrote the plan of the Breakout project on breakout-planned-3, its page showed ● Writing the plan with a link to its run, no milestone bar, and neither "0 of 0 items" nor "No plan is left on disk".

**Confirmed on production (1fc0f22, PR #319); closing.** While run 148 wrote the plan of the Breakout project on `breakout-planned-3`, its page showed `● Writing the plan` with a link to its run, no milestone bar, and neither "0 of 0 items" nor "No plan is left on disk".
Sign in to join this conversation.
No labels
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set

Reference
cmoriarty/braid#318
No description provided.